PROJECT: Enhancement of the pedestrian overlook area of the Logan Street Bridge.
TIMELINE: Scheduled construction began August 8, 2022 and lasted one month. Ribbon Cutting will be held on October 6, 2022.
SCOPE: The Bridge of Flowers will include:
- 1,000 square feet of raised planter box area, of which approximately 230sf will be annuals maintained by Bridge of Flowers volunteers.
- Annuals will be seasonally planted throughout the year by volunteers.
- 90 linear feet of seating area.
- Variable height planter boxes for maintenance by all abilities.
- Two shade structures with overhead lighting.
- Donor recognition area.
OWNER: This is a public/private partnership between the City of Noblesville, Hamilton County, and a local business group.
ENGINEER: DLZ Corporation
CONTRACTOR: Morphey Construction
MILEAGE: 0.1 miles
COUNCIL DISTRICT: 3 (Aaron Smith)
Forms & Applications
Stay Connected
- Thank you to everyone who came out to learn more about #ReimaginePleasantStreet and the important work being done t… https://t.co/irqUVn6oGZRetweeted by City Of Noblesville
- In this week's version of the Friday Five, I update the 10th and Greenfield roundabout improvements, Midland Trace… https://t.co/rluGytk1rdRetweeted by City Of Noblesville
- o Work will not be complete at the end of the 2 weeks, but curbs and pavement will be in place so the roundabout is… https://t.co/G6r9A5rhid
- o During construction, westbound travel on Christian Street and northbound travel on 10th Street will be impacted.… https://t.co/ejpRi74zsf