Herriman Boulevard (Phase 4)
PROJECT: Herriman Boulevard (Phase 4)
TIMELINE: Dependent on the completion of Herriman Boulevard Phase 3 and the construction of State Road 37 and 146th Street.
PROJECT GOALS: Increased mobility and connectivity.
OWNER: City of Noblesville
ENGINEER: USI Consultants
CONTRACTOR: Not awarded
SCOPE: Phase 4 will involve the roadway between DAG/IDI to 146th Street (pictured in red on the map above).
MILEAGE: 0.1 miles
ESTIMATED COST: $300,000
COUNCIL DISTRICT: 5 (Greg O'Connor)
UPDATES
Phase 3 – Part of the SR37/146 Street Project
- Work south of 146th Street began in September and is ongoing. Construction is expected to be mostly complete in the fall of 2020.
- Work north of 146th Street is expected to begin after completion of the south portion.
- Traffic restrictions on Herriman Boulevard are expected to continue until 2021.
Phase 4 – City project
- Construction is expected to take place in 2021, dependent on SR37/146th Street construction. This could be significantly delayed if construction on the interchange is delayed.
- The scope is Herriman Boulevard from DAG/IDI to 146th Street.
Stay Connected
- Republic Services experienced some unforeseen equipment struggles today. @RepublicService continuing to work, but w… https://t.co/2FN3BlsEhn
- #Noblesville Common Council Brian Ayer has decided not to run for another term on the City Council after 20 years o… https://t.co/Qx9VGlO42H
- In this week's Friday Five, I talk about winter weather, a major economic development announcement, the utilities b… https://t.co/nOmx0BzOOFRetweeted by City Of Noblesville
- Winter Weather Update! #Noblesville Street Commissioner Patty Johnson joins me to discuss road conditions and what… https://t.co/ni4ub6fUSKRetweeted by City Of Noblesville