COMPLETE: Presley Blvd Extension - Sanitary Sewer

PROJECT SCOPE/DESCRIPTION
Extend sanitary sewer approximately 335 feet west along Pleasant Street and then 391 feet north along future Presley Blvd. Project will also build road bed for future road Presley Blvd extension.
 
SCHEDULE
Project was bid in March 2009 and completed in Fall 2009.

CITY'S PROJECT MANAGER
Jim Hellmann, PE - Project Manager
 
DESIGN FIRM
City of Noblesville Department of Engineering (In House Design Project)
 
CONTRACTOR
Central Engineering and Construction Associates, Inc.