COMPLETE: SMC Infrastructure (North of 146th St., east of Cumberland Road)

PROJECT SCOPE/DESCRIPTION
Improve Cumberland Road to a 4-lane road with curb and gutter from 146th Street to 150th Street. Extend SMC Blvd. from 150th Street east to Cumberland Road. Project will include trails along Cumberland Road and SMC Blvd.
 
SCHEDULE
Design is complete.
Project was bid in May 2008.
Construction began in July 2008 and was substantially completed in fall 2008. Final work completed in Spring 2009 

CITY'S PROJECT MANAGER
Jim Hellmann, PE
 
DESIGN FIRM
Butler, Fairman, & Seufert (BFS)
 
CONTRACTOR
E&B Paving Inc.