COMPLETE: Town & Country Blvd. and Mercantile Blvd. Intersection Improvements

PROJECT SCOPE/DESCRIPTION
Construct a two lane roundabout to replace stop controlled intersection to improve traffic flow. Add additional left turn lane on Town & Country Blvd. at SR37. Project limits are fronted by Lowe's, Chili's, and O'Charley's.
 
CONSTRUCTION SCHEDULE
Design is complete.
Construction was completed in Spring 2008.

CITY'S PROJECT MANAGER
Andrew Rodewald, EI
 
DESIGN FIRM
Butler, Fairman, & Seufert (BFS)
 
CONTRACTOR
Calumet Civil Contractors

Associated Documents