Project Description

 
Project will relieve congestion at the intersection, increase safety, and alleviate drainage issues in the immediate vicinity. In addition, an asphalt multi-use path will be extended north to connect to Noblesville School campus.
 
The project is being funding 80% with Congestion Management and Air Quality (CMAQ) monies.
 
Utility relocation for the project was completed in August, 2013.

Construction on the roundabout began August, 2013. During Phase I of construction, the roadway will remain open to traffic. However, intermittent delays will be noticed as the contractor mobilizes equipment and material to the site. Three 6-hour closure periods of Hague Road will be scheduled in order for the storm sewer to be constructed across the road. These crossings have been completed, to date.

Phase II of the construction will build the east and west legs of the intersection as well as the center island. During this phase, 196th Street will be closed. This phase began on Monday, September 9, 2013 and has now been completed.

During Phase III of construction, the entire intersection will be closed in order to complete the tie-in of the north and south legs of the roundabout. This work is scheduled to take place during Noblesville Schools Fall Break, October 12 - October 27. This phase has been completed.

The contractor re-mobilized in the spring 2014 in order to complete paving of the multi-use path, do final dirt grading on the site, and complete necessary punch-list items.
 
The project is complete.
 
Bid Opening
 
July 10, 2013
 
Project Start
Utility Relocation: Complete
Roadway: August 22, 2013
 
Closure
Closure 1: Hague Road, South of 196th Street.  Wednesday September 4, 2013 from 9 AM - 2 PM (COMPLETE)
Closure 2: Hague Road, South of 196th Street.  Friday September 6, 2013 from 9 AM - 2 PM (COMPLETE)
Closure 3: Hague Road, South of 196th Street. Monday September 16, 2013 from 9 AM - 2 PM (COMPLETE)

Phase II of construction will close 196th Street east and west of Hague Road - Began Monday, September 9, 2013 (COMPLETE)

Phase III of construction will close entire intersection of 196th Street and Hague Road. Saturday October 12, 2013 - Sunday October, 27, 2013 (COMPLETE)
 

Project Completion
November 2013  (PROJECT COMPLETE)
 
City's Project Manager
Andrew Rodewald, P.E.
Phone: (317) 776-6330
 
Design Firm
City of Noblesville Engineering Department
 
Contractor
Calumet Civil Contractors